BUILDING TASKS
|
|
|
|
for:
|
|
completed:
|
done with or by:
|
|
SITE
|
|
(to be compl)
|
|
|
|
determine location suited to needs
|
2_01
|
employees/ Town
|
|
|
purchase site
|
4_01
|
land owners
|
|
|
boundary survey
|
1_02
|
E.B. Holmberg & Assoc
|
|
|
topographical survey for site engineering
|
2_02
|
Heritage Surveys
|
|
|
wetlands delineation
|
3_02
|
subcontractee through Assoc. Bldrs
|
|
|
perc testing
|
6_01
|
J. Mustain & Board of Health
|
|
|
septic system design
|
3_02
|
J. Mustain
|
|
|
geological analysis / test borings
|
11_03
|
Empire Geo-Services, Inc
|
|
|
stormwater management modeling / report
|
4_02
|
Eric Bernardin,P.E., Associated Bldrs
|
|
|
Notice Of Intent application
|
4_02
|
Eric Bernardin,P.E., Associated Bldrs
|
|
|
Notice Of Intent approval
|
7_02
|
Middlefield Conservation Commission
|
|
|
DEP file number issued
|
7_02
|
Mass Dept. Environmental Protection
|
|
|
~~~all non-installation work related to site
is complete ~~~
|
|
|
|
|
|
|
ARCHITECTURAL DESIGN
|
|
|
|
|
preliminary
|
4_01
|
Crocker Building Co.
|
|
|
early designs for permit presentation
|
4_02
|
Associated Builders, Inc.
|
|
|
redesigned for energy-friendly qualities
|
4_03
|
Rob Blanchard, Architecture Team
|
|
|
Final and construction details
|
(4_04)
|
Rob Blanchard, Architecture Team
|
|
|
|
|
|
|
ENGINEERING DESIGN
|
|
|
|
|
geothermal heat pump design
|
5_03
|
Carl Orio, Water Energy Distributors
|
|
|
HVAC, initial designs
|
9_03
|
E. Lindgren, Lindgren & Sharples,
|
|
|
engineering review of existing/overall plans
|
11_03
|
Hill Engineers
|
|
|
fire protection design 60% complete
|
1_04
|
Chris Cangelosi, P.E., Hill Engineers
|
|
|
fire protection design final
|
(4_04)
|
Chris Cangelosi, P.E., Hill Engineers
|
|
|
HVAC review
|
3_04
|
Chris Cangelosi, P.E., Hill Engineers
|
|
|
site design / grading / stormwater mgmnt
|
3_04
|
Ken Boudreau, Hill Engineers
|
|
|
structural design
|
(4_04)
|
Michael Beatty, P.E., Hill Engineers
|
|
|
Cost estimating
|
3_04
|
Vin Magnano, Hill Engineers
|
|
|
|
|
|
|
ENERGY-RELATED
|
|
|
|
|
Electric Utility & other incentives study
|
1_04
|
Michael Tillou,P.E., etc Group, Inc.
|
|
|
LEED qualification analysis
|
1_04
|
Michael Tillou,P.E., etc Group, Inc.
|
|
|
Life Cycle Cost and Energy Analysis
|
3_04
|
Michael Tillou,P.E., etc Group, Inc.
|
|
|
|
|
|
|
INSTALLATION ON SITE
|
|
|
|
|
haybale silt barrior installed
|
8_ 03
|
local tradesmen
|
|
|
geothermal wells drilled
|
11_01
|
Henshaw Well Drilling
|
|
|
300' of driveway excavated & graveled
|
10_ 03
|
DiNicola Excavating
|