The following chart is of completed or nearly completed tasks before main ground breaking occurs. 

 

BUILDING  TASKS

 

 

for:

 

completed:

     done with or by:

SITE

 

(to be compl)

 

 

determine location suited to needs

2_01

employees/ Town

 

purchase site

4_01

land owners

 

boundary survey

1_02

E.B. Holmberg & Assoc

 

topographical survey for site engineering

2_02

Heritage Surveys

 

wetlands delineation

3_02

subcontractee through Assoc. Bldrs

 

perc testing

6_01

J. Mustain & Board of Health

 

septic system design

3_02

J. Mustain

 

geological analysis / test borings

11_03

Empire Geo-Services, Inc

 

stormwater management modeling / report

4_02

Eric Bernardin,P.E., Associated Bldrs

 

Notice Of Intent application

4_02

Eric Bernardin,P.E., Associated Bldrs

 

Notice Of Intent approval

7_02

Middlefield Conservation Commission

 

DEP file number issued

7_02

Mass Dept. Environmental Protection

 

   ~~~all non-installation work related to site is complete ~~~

 

 

 

 

ARCHITECTURAL DESIGN

 

 

 

preliminary

4_01

Crocker Building Co.

 

early designs for permit presentation

4_02

Associated Builders, Inc.

 

redesigned for energy-friendly qualities

4_03

Rob Blanchard, Architecture Team

 

Final and construction details

(4_04)

Rob Blanchard, Architecture Team

 

 

 

 

ENGINEERING DESIGN

 

 

 

geothermal heat pump design

5_03

Carl Orio, Water Energy Distributors

 

HVAC, initial designs

9_03

E. Lindgren, Lindgren & Sharples,

 

engineering review of existing/overall plans

11_03

Hill Engineers

 

fire protection design 60% complete

1_04

Chris Cangelosi, P.E., Hill Engineers

 

fire protection design final

(4_04)

Chris Cangelosi, P.E., Hill Engineers

 

HVAC review

3_04

Chris Cangelosi, P.E., Hill Engineers

 

site design / grading / stormwater mgmnt

3_04

Ken Boudreau, Hill Engineers

 

structural design

(4_04)

Michael Beatty, P.E., Hill Engineers

 

Cost estimating

3_04

Vin Magnano, Hill Engineers

 

 

 

 

ENERGY-RELATED

 

 

 

Electric Utility & other incentives study

1_04

Michael Tillou,P.E., etc Group, Inc.

 

LEED qualification analysis

1_04

Michael Tillou,P.E., etc Group, Inc.

 

Life Cycle Cost and Energy Analysis

3_04

Michael Tillou,P.E., etc Group, Inc.

 

 

 

 

INSTALLATION ON SITE

 

 

 

haybale silt barrior installed

8_ 03

local tradesmen

 

geothermal wells drilled

11_01

Henshaw Well Drilling

 

300' of driveway excavated & graveled

10_ 03

DiNicola Excavating